Aquifer, Environmental & Geohazard Permits
Development Permit applications for the above were submitted June 2026. They are currently under review and we anticipate approvals by the Town of Gibsons in the near future.
Key Findings presented in Kontur Geotechnical Report:
- Breach likelihood causing aquifer depletion is extremely low.
- Any localized breach can be rapidly mitigated.
- Cutter soil mixing and controlled excavation depths combined with 15m by 15m excavation areas will provide an above standard factor of safety.
- 24 hour monitoring before, during, and after completion of excavation.
- Early Contractor Involvement (ECI) improves risk management.
Form and Character & Archaeological Permits
The application for Development Permit was submitted in July 2026 and is currently under review in conjunction with the Servicing Agreements.
Archaeological permits will be extended to December 2026 while the applications are under review.
Construction Phase & Excavation
Application for Excavation Permit: Additional onsite testing will commence October 2026 with test results and validation completion by the end of November 2026. From this information, detailed design drawings for excavation and shoring will be prepared for submission and review by the Town.
The Excavation Permit application is scheduled to be submitted to the Town of Gibsons in February 2027.
Start of Construction: Construction is slated to start early 2027, pending Town approval of permits within timelines.